ARTONDALE ELEMENTARY SCHOOL

PENINSULA SCHOOL DISTRICT

2022 Completion

$28.8M

2022


Designed by Integrus and built by LCi, the replacement
of Artondale Elementary School occurred on a fully occupied, operational campus. The new school is 77,175 sf, two-story building with 3,822 sf covered play structure, and site improvements including new playfields, parking, and bus/parent drop-off.  

A challenge that LCi successfully navigated was the electrical utility’s inability to provide sufficient power concurrently to both the existing school and the newly built school. LCi’s solution was to provide generator support and temporary tie-ins to the new school so that systems could be tested and commissioned while school operations continued in the existing school.

 

 